3rd water-crossing permit suspended on Mountain Valley Pipeline

% of readers think this story is Fact. Add your two cents.


Pittsburgh, PA — At the request of a coalition of clean water advocates, the Pittsburgh District of the Army Corps of Engineers late Friday suspended a third permit that the fracked gas Mountain Valley Pipeline (MVP) must have to build through waterways for its project. This permit affected waterways in Wetzel and Harrison counties in West Virginia, which is under the district’s jurisdiction.

The move follows MVP’s loss of a stream crossing permit in southern West Virginia in a federal court decision, and the Corps’ suspension of a similar permit for MVP’s Virginia stream crossings. MVP is required to have Nationwide Permit 12 authorizations from three Corps districts in order to continue construction; it now has zero. As a result, MVP is now prohibited from any construction in any stream or wetland in its path.

The clean water advocates who brought this challenge are now calling on Federal Energy Regulatory Commission (FERC) to halt all work on the pipeline, as FERC’s order approving the project requires that all permits be in place for construction to take place anywhere along its 303-mile route.

The action is the result of an October 11, 2018, request to the Corps by attorneys from Appalachian Mountain Advocates on behalf of the Sierra Club, West Virginia Rivers Coalition, West Virginia Highlands Conservancy, Indian Creek Watershed Association, New River Conservancy, Appalachian Voices, and Chesapeake Climate Action Network.

Joan Walker, Sierra Club Beyond Dirty Fuels Campaign Representative:

“No matter the area, there is no way to build fracked gas pipelines that doesn’t endanger or water, our communities, or our climate. We’re pleased to see today’s suspension, and demand that FERC immediately halt all construction on the dirty and dangerous Mountain Valley Pipeline. We cannot allow corporate polluters to lock us in to decades more of fossil fuels when clean, renewable energy is available and ready to use now.”

Derek Teaney, Senior Attorney at Appalachian Mountain Advocates:

“The Pittsburgh District did the right thing in granting our request to suspend MVP’s last stream crossing permit. Now the ball is in FERC’s court to put a stop to upland construction. Not only is continued construction unlawful, but it makes no sense–environmentally, financially, or otherwise–to allow MVP to install its pipeline in between streams and wetlands now and just assume that it will ultimately be able to come back later and complete its stream crossings. It is surprising that FERC hasn’t yet put a stop to this illegal, wasteful, and inefficient construction method that MVP is undertaking.”

Howdy Henritz, Indian Creek Watershed Association President:

“This is welcome news, but the FERC must now issue a Stop Work Order for all MVP construction activities along its entire route. Muddy water has been spewing into our waterways from upland construction. It is outrageous that FERC has allowed MVP to continue upland construction without having all required permits. The environmental costs borne by landowners today as MVP construction continues unabated is unconscionable. The financial costs to be borne by gas customers in the future will be intolerable.

Angie Rosser, West Virginia Rivers Coalition Executive Director:

“FERC must apply the brakes on this project. The unlawful permitting of this project proves the old adage, ‘haste makes waste’. We simply can’t afford more waste in our streams for the benefit of multi-billion dollar corporations who can shift the financial consequences of its haste ultimately upon its customers.”

Anne Havemann, General Counsel at Chesapeake Climate Action Network:

“Friday’s suspension makes clear yet again that the permits hastily given to the fracked-gas Mountain Valley Pipeline don’t stand up to scrutiny. Key permits for the Mountain Valley Pipeline have been thrown out again and again, confirming that this pipeline — and the similarly destructive Atlantic Coast Pipeline — is too dangerous to ever be built. Despite this, construction for most of this dangerous pipeline continues. FERC must issue a stop-work order on the entire pipeline — to do otherwise is completely unacceptable.”

Lara Mack, Virginia Field Organizer, Appalachian Voices:

“Now that construction has been ordered to stop at all 1,146 water crossings along MVP path, it is of paramount important that FERC issue a stop work order for all construction on the project. EQT said they would build the pipeline safely and in a way that protects our natural resources, but work has resulted in injured workers, pipes floating off construction sites after heavy rains, and multiple creeks and streams clogged with mud and other problems. To make matters worse, the company has yet to truthfully justify the need for the project.”

CONTACT:
Jonathon Berman, Sierra Club, [email protected]
Cat McCue, Appalachian Voices, [email protected]; 434-293-6373

###

The post 3rd water-crossing permit suspended on Mountain Valley Pipeline appeared first on Appalachian Voices.

Protecting the Central and Southern Appalachian Mountain Region


Source: http://appvoices.org/2018/10/22/3rd-water-crossing-permit-suspended-on-mountain-valley-pipeline/


Before It’s News® is a community of individuals who report on what’s going on around them, from all around the world.

Anyone can join.
Anyone can contribute.
Anyone can become informed about their world.

"United We Stand" Click Here To Create Your Personal Citizen Journalist Account Today, Be Sure To Invite Your Friends.

Please Help Support BeforeitsNews by trying our Natural Health Products below!


Order by Phone at 888-809-8385 or online at https://mitocopper.com M - F 9am to 5pm EST

Order by Phone at 866-388-7003 or online at https://www.herbanomic.com M - F 9am to 5pm EST

Order by Phone at 866-388-7003 or online at https://www.herbanomics.com M - F 9am to 5pm EST


Humic & Fulvic Trace Minerals Complex - Nature's most important supplement! Vivid Dreams again!

HNEX HydroNano EXtracellular Water - Improve immune system health and reduce inflammation.

Ultimate Clinical Potency Curcumin - Natural pain relief, reduce inflammation and so much more.

MitoCopper - Bioavailable Copper destroys pathogens and gives you more energy. (See Blood Video)

Oxy Powder - Natural Colon Cleanser!  Cleans out toxic buildup with oxygen!

Nascent Iodine - Promotes detoxification, mental focus and thyroid health.

Smart Meter Cover -  Reduces Smart Meter radiation by 96%! (See Video).

Report abuse

    Comments

    Your Comments
    Question   Razz  Sad   Evil  Exclaim  Smile  Redface  Biggrin  Surprised  Eek   Confused   Cool  LOL   Mad   Twisted  Rolleyes   Wink  Idea  Arrow  Neutral  Cry   Mr. Green

    MOST RECENT
    Load more ...

    SignUp

    Login

    Newsletter

    Email this story
    Email this story

    If you really want to ban this commenter, please write down the reason:

    If you really want to disable all recommended stories, click on OK button. After that, you will be redirect to your options page.