Tesla Gigafactory 3 Phase 1 enters roof paving stage ahead of May 2019 target

% of readers think this story is Fact. Add your two cents.


A recent flyover of Gigafactory 3 has revealed that the upcoming electric car factory continues to follow an incredibly rapid buildout, with the first phase of the project seemingly entering the roof paving stage.

The flyover of the Gigafactory 3 site was conducted once more by China-based Wuwa Vision (烏瓦), a drone operator who has been following the progress of the construction since last October. Between the drone operator’s previous trip on the site back on April 5 and this recent flyover, significant progress appears to have made in the site’s Phase 1 section, which is expected to correspond to the construction of a general assembly building.

Compared to previous videos taken of the site, more roof trusses are now in place, and some workers are now paving some areas of the general assembly building’s steel roof structure. More steel foundations appear to have been laid as well, and the framework of what seems to be a multi-story section is currently being built.

Similar to previous flyovers, the 864,885-square meter site continues to be abuzz with activity, with dozens of heavy machinery working continuously alongside a workforce that works on the project 24/7. The site’s round-the-clock operating schedule was mentioned in a previous video by a worker employed in the project, who confirmed that activities in Gigafactory 3 does not stop.

What is particularly remarkable is that the construction of Gigafactory 3 has only started a couple of months ago. Elon Musk visited China in early January for the facility’s groundbreaking ceremony, and in the span of just three months, the Gigafactory 3 site has been transformed from a large muddy field into an area where a massive general assembly building is taking shape. This pace serves the project well, considering that Shanghai official Chen Mingbo has given the project a May 2019 target date for completion.

Tesla Automotive President Jerome Guillen and Shanghai Deputy Mayor Wu Qing recently held a meeting about the progress of the facility’s buildout, where they discussed, among other things, the initial setup of vehicle production equipment starting this May, according to reports from local news media who covered the event. Based on this timeframe, it appears that Tesla is aiming to start preparing the site for vehicle production while construction in other areas of the 864,885-square meter lot are still ongoing.

Watch the recent Gigafactory 3 flyover in the video below.  

The post Tesla Gigafactory 3 Phase 1 enters roof paving stage ahead of May 2019 target appeared first on TESLARATI.


Source: https://www.teslarati.com/tesla-gigafactory-3-general-assembly-building-roof-paving/


Before It’s News® is a community of individuals who report on what’s going on around them, from all around the world.

Anyone can join.
Anyone can contribute.
Anyone can become informed about their world.

"United We Stand" Click Here To Create Your Personal Citizen Journalist Account Today, Be Sure To Invite Your Friends.

Please Help Support BeforeitsNews by trying our Natural Health Products below!


Order by Phone at 888-809-8385 or online at https://mitocopper.com M - F 9am to 5pm EST

Order by Phone at 866-388-7003 or online at https://www.herbanomic.com M - F 9am to 5pm EST

Order by Phone at 866-388-7003 or online at https://www.herbanomics.com M - F 9am to 5pm EST


Humic & Fulvic Trace Minerals Complex - Nature's most important supplement! Vivid Dreams again!

HNEX HydroNano EXtracellular Water - Improve immune system health and reduce inflammation.

Ultimate Clinical Potency Curcumin - Natural pain relief, reduce inflammation and so much more.

MitoCopper - Bioavailable Copper destroys pathogens and gives you more energy. (See Blood Video)

Oxy Powder - Natural Colon Cleanser!  Cleans out toxic buildup with oxygen!

Nascent Iodine - Promotes detoxification, mental focus and thyroid health.

Smart Meter Cover -  Reduces Smart Meter radiation by 96%! (See Video).

Report abuse

    Comments

    Your Comments
    Question   Razz  Sad   Evil  Exclaim  Smile  Redface  Biggrin  Surprised  Eek   Confused   Cool  LOL   Mad   Twisted  Rolleyes   Wink  Idea  Arrow  Neutral  Cry   Mr. Green

    MOST RECENT
    Load more ...

    SignUp

    Login

    Newsletter

    Email this story
    Email this story

    If you really want to ban this commenter, please write down the reason:

    If you really want to disable all recommended stories, click on OK button. After that, you will be redirect to your options page.