Mountain Valley Pipeline Ordered to Halt Construction at Stream Crossings

% of readers think this story is Fact. Add your two cents.


Mountain Valley Pipeline construction. Photo courtesy of Appalachians Against Pipelines

By Appalachian Voices staff

Construction of the Mountain Valley Pipeline is now halted at nearly all stream crossings in West Virginia and Virginia, following a court ruling from last week. This is in addition to a July court-mandated halt to construction in the Jefferson National Forest.

On Oct. 2, the U.S. Fourth Circuit Court of Appeals vacated a necessary Clean Water Act permit needed for the Mountain Valley Pipeline to be constructed across streams and waterways throughout most of its proposed route in West Virginia.

Then, on Friday, Oct. 5, the U.S. Army Corps of Engineers suspended the permit granting Mountain Valley Pipeline permission to cross 383 stream crossings and 142 wetland crossings in Virginia. The Roanoke Times reported that a letter to Mountain Valley from William Walker, chief of the regulatory branch of the corps’ Norfolk division, stated that the permit was pulled to halt construction while they “await clarity on this issue.”

The case centered on Mountain Valley’s inability to comply with a West Virginia condition requiring that stream crossings be completed in 72 hours or less to qualify for the broader, one-size-fits-all Clean Water Act permit, known as Nationwide Permit 12, that the Army Corps of Engineers used. The record showed Mountain Valley Pipeline would need far longer to build across some of the larger rivers along the route.

“The immediate halt of construction in Virginia and West Virginia is important to the landowners in the pipeline’s path who have carried the burden of experiencing MVP’s faulty construction practices and damages to numerous waterways this year,” Appalachian Voices’ Virginia Field Organizer Lara Mack told the Roanoke Times. “Their suffering is especially egregious due to the utter lack of evidence that more pipeline capacity is even needed in our region.”
The court’s order is a victory for nonprofit law firm Appalachian Mountain Advocates, which represented Appalachian Voices alongside the Sierra Club, West Virginia Rivers Coalition, Indian Creek Watershed Association and Chesapeake Climate Action Network.

In the wake of the ruling, Appalachian Mountain Advocates expects the Corps may now have to conduct “a significant environmental assessment” to issue an individual Clean Water Act permit for the pipeline instead of the broader permit. The groups are now arguing that the Federal Energy Regulatory Commission should issue a stop-work order for the entire pipeline because the certificate that gives Mountain Valley permission to proceed is contingent upon securing all other required federal permits.

“The court’s decision validates what citizens and pipeline opponents have been saying all along — the permitting process for the Mountain Valley Pipeline was fatally flawed, allowing pipeline developers to rush into construction without regard for the devastation to water resources in West Virginia and Virginia,” AppVoices’ Virginia Program Manager Peter Anderson said in a press statement. “We’ve seen this broken approach at every level, starting with FERC’s decision to certify a 300-mile, 42-inch diameter pipeline, despite the lack of evidence that the region even needs any new pipeline capacity.”

According to ProPublica and the Charleston Gazette-Mail, West Virginia regulators are merely rewriting their rules to allow the project to proceed, instead of considering the ramifications of the pipeline. West Virginia’s Department of Environmental Protection recently held a comment period to receive public input on this proposed change. The comment period closed on September 17 and West Virginia residents and our partners expect to see a response from WVDEP any day now. After this process is completed, Mountain Valley would apply for a new permit, expected in early 2019.

While Virginia does not impose the same 72-hour condition on construction, there is a similar case pending at the Fourth Circuit. Petitioners argue that the invalid West Virginia permit renders the Virginia permit invalid as well.

Actions against the Mountain Valley Pipeline have already taken a large toll; on Sept. 24, the private companies behind the pipeline announced the cost of the project was raised to $4.6 billion, a nearly $1 billion increase. And that was before these latest delays, which could have a significant impact on the completion of the pipeline. In the meantime, there is no doubt that these delays are protecting precious water sources for another day. And that counts for a lot.

Two actions you can take to continue the fight to STOP the Mountain Valley Pipeline

  • Help monitor and document construction of the Mountain Valley Pipeline! Learn more about the Mountain Valley Watch network led by POWHR Coalition at powhr.org/mvwatch.
  • Call Virginia Governor Northam! Tell him about the court decision and that he must do more to protect SWVA communities and our precious water resources! 804-786-2211

The post Mountain Valley Pipeline Ordered to Halt Construction at Stream Crossings appeared first on Appalachian Voices.

Protecting the Central and Southern Appalachian Mountain Region


Source: http://appvoices.org/2018/10/11/mountain-valley-pipeline-ordered-to-halt-construction-at-stream-crossings/


Before It’s News® is a community of individuals who report on what’s going on around them, from all around the world.

Anyone can join.
Anyone can contribute.
Anyone can become informed about their world.

"United We Stand" Click Here To Create Your Personal Citizen Journalist Account Today, Be Sure To Invite Your Friends.

Please Help Support BeforeitsNews by trying our Natural Health Products below!


Order by Phone at 888-809-8385 or online at https://mitocopper.com M - F 9am to 5pm EST

Order by Phone at 866-388-7003 or online at https://www.herbanomic.com M - F 9am to 5pm EST

Order by Phone at 866-388-7003 or online at https://www.herbanomics.com M - F 9am to 5pm EST


Humic & Fulvic Trace Minerals Complex - Nature's most important supplement! Vivid Dreams again!

HNEX HydroNano EXtracellular Water - Improve immune system health and reduce inflammation.

Ultimate Clinical Potency Curcumin - Natural pain relief, reduce inflammation and so much more.

MitoCopper - Bioavailable Copper destroys pathogens and gives you more energy. (See Blood Video)

Oxy Powder - Natural Colon Cleanser!  Cleans out toxic buildup with oxygen!

Nascent Iodine - Promotes detoxification, mental focus and thyroid health.

Smart Meter Cover -  Reduces Smart Meter radiation by 96%! (See Video).

Report abuse

    Comments

    Your Comments
    Question   Razz  Sad   Evil  Exclaim  Smile  Redface  Biggrin  Surprised  Eek   Confused   Cool  LOL   Mad   Twisted  Rolleyes   Wink  Idea  Arrow  Neutral  Cry   Mr. Green

    MOST RECENT
    Load more ...

    SignUp

    Login

    Newsletter

    Email this story
    Email this story

    If you really want to ban this commenter, please write down the reason:

    If you really want to disable all recommended stories, click on OK button. After that, you will be redirect to your options page.